Timeline

February 15-29, 2012      The Core Platform will be installed.

April 9-30, 2012                 The First 250 Instructional Learning(classrooms/labs) PCs will be activated.

  • AMG 214
  • SAEC (Student Athlete Enhancement Center)
  • KUC 326-S
  • COE 104
  • COE 110
  • HON 118
  • Library (~20 PCs)

 

March 5-30, 2012              The first 100 MTSU employee PCs will be activated.

  • ~50 Desktops in the Business & Finance Dept.
  • ~50 Desktops in ITD

April 16, 2012                     Begin the rollout for University employees and Instructional Learning PCs.

August 25, 2012                  The remote access schedule to be activated.